96 Fix Project Bridge Closures Updated

Livonia, MI - As part of the 96 Fix project in Livonia, MDOT has released a list of bridges over I-96 that are affected by construction.

The following is a current list of bridges over I-96 that are open, closed, or scheduled to be closed soon:

 

Bridge #

Road Name

Status

Closure Type

Estimated Reopening

1

Schoolcraft Road

Open

 

 

2

Newburgh Road westbound U-turn

Closed

Full closure

October

3

Newburgh Road

Under construction

One lane open in each direction*

Mid-July

4

Newburgh Road eastbound U-turn

Closed

Full closure

Mid-May

5

Levan Road westbound U-turn

Closed

Full closure

Late May

6

Levan Road

Open

 

 

7

Levan Road eastbound U-turn

Closed

Full closure

Late May

8

Yale Street

Open

 

 

9

Wayne Road

Closed

Full closure

Late May

10

Stark Road

Open

 

 

11

Farmington Road westbound U-turn

Open

 

 

12

Farmington Road

Open

 

 

13

Farmington Road eastbound U-turn

Open

 

 

14

Brookfield Street

Closed

Full closure

Late May

15

Berwick Street

Open

 

 

16

Merriman Road westbound U-turn

Open

 

 

17

Merriman Road

Open

 

 

18

Merriman Road eastbound U-turn

Open

 

 

19

Warner Court

Closed

Full closure

Mid-June

20

Melvin Street

Open

 

 

21

Middlebelt Road westbound U-turn

Closed

Full closure

Late May

22

Middlebelt Road

Open

 

 

23

Middlebelt Road eastbound U-turn

Closed

Full closure

Mid-May

24

Racetrack Drive

Open

 

 

25

Cardwell Street

Open

 

 

26

Inkster Road westbound U-turn

Closed

Full closure

Mid-May

27

Inkster Road

Closing mid-May

Full Closure

Mid-July

28

Inkster Road eastbound U-turn

Closed

Full closure

Mid-May

29

Breakfast Drive

Open

 

 

30

Berwyn Avenue

Closed

Full closure

Mid-May

31

Beech Daly Road westbound U-turn

Closing mid-May

Full Closure

Mid-June

32

Beech Daly Road

Open

 

 

33

Beech Daly Road eastbound U-turn

Closing mid-May

Full Closure

Mid-June

34

Garfield

Closed

Full closure

Mid-May

35

Fenton

Open

 

 

36

US-24 southbound service drive

Construction starts mid-May

Two lanes open at all times

Mid-July

37

US-24 northbound service drive

Closed

Full closure

Mid-May

 

 

 

 

 

* Additional turning restrictions at Newburgh Road. Follow posted detour signage.

TRAFFIC IMPACT: Motorists will be detoured to the next available bridge.

PROJECT DETAILS:
The 96 Fix project between Newburgh and Telegraph roads involves reconstructing the freeway, repairing 37 overpasses and upgrading utilities. I-96 will be closed throughout the project, and is expected to reopen in October.

For more information on this $148 million investment, go to the project website at www.96fix.com.